Jump to content

Projects in the UK

Tregonning Solar Farm and Co-located Battery Storage Facility

Project Location

The solar farm is located on approximately 88 hectares of farmland near Kestle Mill, Cornwall.

The Battery Energy Storage System is located at Indian Queens, directly adjacent to the National Grid Energy Transition (NGET) Indian Queens 400kV Substation.

The project includes an approximately 8.5km underground 33kV cable connection between the solar farm, the BESS and the grid connection point east of the A30.

No overhead power lines are proposed as part of this project.

Planning Background and Project Organisation

Planning permission for the solar farm was granted in December 2023. The project was initially developed and taken through planning by Renewable Connections and was acquired by European Energy post‑consent.

European Energy is delivering the solar farm, with Novus Power appointed as Principal Contractor for the BESS and underground cable route.

Construction Programme

The solar farm construction programme broadly includes:

  • Site setup (temporary access roads, compound and fencing)
  • Installation of solar panels and mounting systems
  • Electrical infrastructure, including cabling and on‑site substation
  • Testing and commissioning
  • Final landscaping and reinstatement

Construction is expected to complete by spring 2027, following which the site will operate quietly with minimal vehicle movements.

Working Hours

Construction working hours are strictly controlled:

  • Monday–Friday: 8:00am – 6:00pm
  • Saturday: 9:00am – 1:00pm
  • No Sunday or Bank Holiday working
Construction

Construction Timeline

Site preparation works for Tregonning Solar Farm will begin in the Spring of 2026 and construction will follow the phases as laid out below

  1. Phase 01

    Site Preparation

    Installing access roads, fencing, substations, and power lines

  2. Phase 02

    Foundation and Mounting Installation

    Laying foundation Assembling mounting frames

  3. Phase 03

    Solar Panels and Electrical Systems

    Placing panels and connecting electrical systems

  4. Phase 04

    Grid Connection and Testing

    Connecting to the grid, comprehensive testing

  5. Phase 05

    Landscaping, Restoration

    Finalizing landscaping, restoring the site

BESS Construction and Operation

  • Site mobilisation is planned from May 2026
  • Working hours:
    • Monday–Friday: 8:00am – 6:00pm
    • No Bank Holiday or weekend working
    • No deliveries after 4:00pm on weekdays

Once built, the BESS will operate quietly and largely invisibly, with only occasional maintenance visits.

Where possible, deliveries are scheduled outside peak traffic times to minimise disruption.

How the Cable Works Will Be Carried Out

  • Cable installation will progress in short sections along the route
  • Trenches will be excavated, ducts installed, cables laid and surfaces reinstated
  • Works will be carefully coordinated around existing utilities
  • Road access for residents, businesses and emergency services will be maintained at all times
  • Temporary traffic management will be in place where required


Cable Works -Working Hours and Mobilisation

Cable Works site mobilisation: late June 2026

Working hours:

Monday–Friday: 8:00am – 6:00pm
No weekend or Bank Holiday working
No weekday deliveries after 4:00pm

Traffic measures include:

Temporary Traffic Regulation Orders where necessary
Advance notice to affected residents and businesses

Clearly signed diversion routes

HGV routing via main roads and major junctions, avoiding narrow village roads wherever possible

Communications / Cyfathrebu

We understand the importance of open communication and transparency. Throughout the construction process, we are committed to keeping you well-informed about project developments, timelines, and any potential impacts on the local area. Regular updates will be provided through this site, through contact from our UK team and through channels agreed with the local community.

Tregonning Solar Farm

News and Updates

  • Tregonning Project update and a new community meeting

  • Taking a Moment to Reflect This Spring

  • Tregonning Solar Farm Information Evening

  • Tregonning Solar Farm Information Evening

Tregonning Solar Farm

Latest updates

Updates for construction activities in 2026

  • Type: pdf

Tregonning Solar Farm

Images from around Tregonning Solar Farm

European Energy Team

Contacts

Your feedback is valuable to us, and we encourage you to reach out with any questions or concerns. We are dedicated to fostering collaborative and positive relationships as we work together toward a sustainable future.

Lisa Wilson

Project Communications Manager

(+44) 75 08 81 71 13